Every molding machine has to shut down periodically for a mold set-up. Unfortunately,
machines are commonly out of action far longer than necessary due to avoidable
mistakes in set-up procedures. A poorly planned or executed mold set-up can
resemble a comedy of errors. When the machine is started up again, the result
can be slow cycles, high scrap rates, tool damage, defective parts, rework,
an unstable process, late delivery of product, and the loss of profit margin
on the job.
Since it opened in 1984, Donnelly Custom Manufacturing has embraced the challenge
of perfecting the mold changeover process rather than just accepting it as a
necessary chore. Along the way, we have acquired some insight on avoiding common
mistakes. Getting change-overs right is particularly important to our focus
on short-run manufacturing. Our approach works: Mold- change times have been
trimmed by 50% over the past two years, and were now able to complete
many changeovers for smaller presses in less than 30 min and for our largest
presses within 2 hr.
|
Donnelly trimmed tool set-up time with two-member teams that work on both sides
of the press simultaneously and with tool change carts that are prepared in
advance with all the tools and parts needed for the changeover.
|
Donnelly has 27 injection presses from 28 to 720 tons, executes an average of
30 (and as many as 55) mold changes a day, and usually performs from 190 to
210 set-ups weekly. Some production runs can be as short as 15 min, although
a 10-hr run is the average. An extra 10 min on set-up can erase the profit on
a run of less than 2 hr.
TIP No. 1
Avoid Unnecessary Idling
At many molders, once the press completes its last cycle, it typically is shut
down and sits idle while the changeover crew takes out the finished mold and
puts it away, locates and retrieves the next mold, stages any required auxiliary
equipment, and finally conducts the set-up.
We recommend pre-staging the next mold changeover while the press is still in
production with the current mold. Use a set-up cart that contains all of the
tools necessary to tear down and set up the mold. The cart should include torque
wrenches, impact wrenches, mold clamps and bolts, nozzles, cleaners, and any
other equipment required. A member of the crew should go over the set-up cart
during the pre-staging effort to ensure it isnt missing any essential
items. Pre-staging helped Donnelly shave as much as 33% off the average changeover
time.
Scheduling and staging material in time is also critical. Many materials require
pre-drying from 2 to 6 hr before processing. Failure to adequately schedule
and pre-stage the material has the potential to idle a press much longer than
the rest of the changeover activities combined.
Prioritize the set-up crews activities: Concentrate on getting the new
mold up and running first, not on putting the just-removed mold into storage.
Theres time for that after the changeover is complete and production resumes.
TIP No. 2
Organize Mold Storage
A trouble spot for many molders is mold storage. They often waste time finding
and retrieving molds. Part of the problem is inefficient ways of storing and
inventorying molds. Another part of the problem is storing molds too far away
from the press. To improve mold storage and retrieval, Donnelly built what we
call mold grandstands. They resemble high-school bleachers (see photo) and are
located adjacent to the press. Every mold is assigned a place on a specific
rack, and each mold is numbered. The most frequently run molds are stored where
they are easiest to reach. So, when a mold is needed, one of the crew performing
the changeover needs only to walk across the aisle to retrieve the mold. An
overhead crane is used to transport the molds. We have separate grandstands
for small and medium-size molds, while the larger molds are stored on a vertical
racking system near the large injection machines.
TIP No. 3
Follow a Checklist
In the absence of a defined process for changeovers, molders may face long start-ups
and other challenges that adversely affect market competitiveness. Establishing
a checklist for the tools and steps for mold connection to the press is vital.
Production supervisors at Donnelly use the checklist to make sure each scheduled
changeover was completed and to evaluate how well it was done. Donnelly analyzes
every changeover and looks for ways to improve the process. Even non-machine-related
factors, such as material drying, can be reviewed closely for areas of improvement.
In fact, we go so far as to create an instruction manual for each of the molds
we run. It includes checking the first and last parts in a job run for signs
of warpage, flashing, mold wear, and other process maladies. We also have a
checklist for the auxiliary equipment used, which is a part of the work order.
TIP No. 4
Commit to Training
Sometimes mold set-ups are protracted simply because there are too few people
in the shop qualified to execute a mold changeover. In even a small molding
shop, it is not uncommon to have several machines due for mold set-ups at the
same time. Yet many molders rely on just one or two specialists. That means
presses may remain idle while specialists are bogged down during busy periods
or difficult set-ups.
|
Tool changes go faster when the mold is stored near the machine and is clearly identified. Donnelly developed mold-storage grandstands near each of its 27 presses. Each mold is assigned a particular space.
|
This can be avoided by training press operators to do mold changeovers. Donnelly
has trained 40% of its hourly personnel for this task. Not only can all changeovers
be done in a timely fashion, but set-up times have also been reduced since press
operators are able to pitch in and help in all phases of the process. Shift
supervisors now create ad hoc changeover teams of certified molding operators
on a daily basis, rather than having only one person or one crew perform them.
Donnelly also has a proven formula for executing changeovers: Always use two-person
teams, regardless of press size. The team members have defined roles and work
one on each side of the press. Over half the 60 people trained to perform mold
changeovers at Donnelly are women.
TIP No. 5
Communicate Effectively
Production schedules change unexpectedly. This leaves many molding firms scrambling
to address issues of who, what, where, when, and how right before a press is
due to be changed. Often the result is that the press sits idle longer than
necessary.
One way to avoid this situation is to conduct daily production meetings. Donnelly
uses a Manufacturing War Room concept developed by International
Plastics Consulting Corp. in Stamford, Conn. Daily meetings are held between
cross-functional teams to review and discuss the job schedule and make assessments
of priorities and resources. The daily meetings help to anticipate and minimize
unplanned glitches throughout the manufacturing sequence, including mold change-overs.
Any problem that can affect part production, quality, and delivery is placed
on a board in the Manufacturing War Room and is resolved within 48 hr.
It pays to get as much feedback as possible from everyone associated with the
mold-change process. Doing so helps ensure the process is continually honed.
And you never know where the next good idea will originate.
TIP No. 6
Dont Neglect Maintenance
A common mistake among molders is to compromise on equipment maintenance. A
broken ejector pin, stripped-out bolt hole on a platen, or a worn check ring
will delay the successful start up of a mold.
Based in Alexandria, Minn., Donnelly is a custom injection molder with more
than 200 employees, Dave Lamb is director of manufacturing; Brad Andrist is
training and continuous-improvement coordinator.